Hello,
I have a question regarding the power-up sequence of the AD5144A.
The AD5144A datasheet specifies the following ideal power-up sequence:
VSS → VDD → VLOGIC → digital inputs → VA/VB/VW
I would like to clarify the requirements for VSS, VDD, and VLOGIC.
-
Why is the order VSS → VDD → VLOGIC recommended?
Is there any internal circuit or device reliability reason that requires VSS to be powered before VDD, and VDD before VLOGIC? -
Is it acceptable to power up VSS, VDD, and VLOGIC simultaneously?
In our application, these power supplies may start rising at approximately the same time. -
Is the specified sequence VSS → VDD → VLOGIC a mandatory requirement, or is it only an ideal/recommended sequence?
We understand that VA, VB, and VW should not be applied before the power supplies are established because of the internal protection diodes.
Could you please clarify whether simultaneous power-up of VSS, VDD, and VLOGIC is allowed and whether there are any restrictions on their relative ramp timing?
Best regards,